Project: CBJTC Barracks 2108-2113 Demo and Replacement at Camp Blanding Joint Operations Command Training Facility, Starke, FL
Scope: Demo four barracks buildings and one latrine facility plus additional administration building. New construction of five new barracks buildings (including latrine facilities in each.) Buildings were constructed of block construction with standing seam metal roof with energy efficient mechanical and electrical equipment installed. All utilities required replacing and/or modifications. New drainage system and sitework required to accommodate new latrines in each building. New buildings were required to be built on the existing footprint with no additional square footage allowed.
Project: FED Warehouse/Office Build-out at Camp Blanding Joint Operations Command Training Facility, Starke, FL
Scope: New Construction of a pre-engineered Metal Building with both warehouse and office space. Warehouse had roll-up doors and utility doors. Office area was air-conditioned with drop ceilings, drywall finish, VCT flooring, storefront windows and doors, and some minor millwork. The exterior had an entry feature and a small parking area. Modifications required a retention pond be added for stormwater increase.
Project: Joint Operations Center Training Facility (JOCTF) at Camp Blanding Joint Operations Command Training Facility, Starke, FL
Scope: This 12,000 sq ft facility featured ICF walls, ISO insulation, interior masonry walls, computer-controlled HVAC systems, interior storefront systems, metal roof system, metal truss systems with certified welding connections for 160 MPH design, computer access floor system, draft and firewall construction to eliminate need for sprinkler systems which would damage sensitive computer equipment. Due to the complexity of this project, there were unforeseen challenges. KBT addressed each challenge and completed the project at the highest level of quality and a competitive value. Additionally, this project was designed and built to meet LEED silver standards even though it was not officially registered as a LEED project with the USGBC. KBT was still required to meet all LEED Silver requirements. The building also serves as the “Emergency Location” for the Florida State Legislature.
Project: Design/Build – Main Gate and Perimeter Fence at Camp Blanding Joint Operations Command Training Facility, Starke, FL
Design/Build services for the construction of approximately ½ mile of Brick/Masonry, column, knee wall and metal fencing at the Main Gate of Camp Blanding. There were very strict security guidelines that had to be followed which presented many challenges with materials and site conditions. Funding was provided through set-aside money under the Patriot Act. Specifications for Antiterrorism Force Protection (ATFP) and had to be strictly adhered to. This presented many challenges because elevations in civil design had to maintain architectural integrity and still meet Force protection requirements. KBT’s successful completion of Phase I lead to KBT being awarded Phase II for an additional ¼ mile of wall and fencing 2 years later as a negotiated contract under our Construction Manager at Risk contract. ATFP requirements were still in effect for this portion of the fence.
Project: VOR Roof Refurbishment, Waycross, GA
Scope: Construction of new roofing and antennas for a VOR facility located in Waycross, GA. The project title is deceptive because it consists of many different parts and disciplines including but not limited to:
PROJECT: EVER251236 – Harden Facilities with Hurricane Resistant Windows (Irma) Everglades National Park, FL
Scope: Negotiated 8(a) Design/Build contract for the replacement of non-impact resistant windows and storefront systems with hurricane impact resistant windows and storefront systems to mitigate potential storm damage, while adhering to all the requirements of the Florida Building Codes, Miami/Dade NOA and any other applicable codes and standards at three (3) historical buildings and thirty-one (31) non-historic buildings within the Everglades National Park. Challenges include remote location, maintaining historic integrity, and coordination of material deliveries. Additional requirement to install Level 5, bulletproof glass at main entry into Park for Antiterrorism Force Protection.
Project: Museum Renovations – Cumberland Island National Seashore, St. Marys, GA
Scope: Installed four large format print images behind the custom fabricated wooden window frames on the exterior of the building. Replaced the existing automatic opening ADA door with a new custom fabricated wood door. Existing automatic openers and hardware were reused. Enlarged the existing interior alcove by relocating the two restroom walls and relocated the restroom entrance doors, KBT was responsible for maintaining ADA compliance. Removed and replaced all the ceramic floor tile in the main entrance alcove. Constructed an enclosure wall to allow the main area to stay open and separate during construction. Relocated low-voltage receptacle. Repaired tile. Relocated fire alarm and fire extinguishers.
Project: Prep & Paint Main House and Kitchen at Timucuan Ecological and Historic Preserve, Jacksonville, FL
Scope: Prepped and painted the exterior of the Main House, Kitchen Building, and Breezeway at the Kingsley Plantation (approximately 10,000 sq ft of wood surfaces). Power-washed the underside of porch roofs, all decking, stairs and railings, all roof decorative features including widow walks, and north elevation siding where existing paint was properly adhered, using a 65-degree soap/chemical nozzle at no more than 50 PSI for applying a cleaning solution and rinsing off the building. All loose paint was scraped or sanded, and rough edges hand sanded to “feather in”. KBT was Prime Contractor and self-performed the entire project.
Project: Weapons Clearing Structure Bldg. 1591, NS Mayport, FL
Scope: Design/Build project to remove and replace the existing weapons clearing structure behind building 1591 with a new wood framed structure. Project was completed 27 days early with zero punch items required at final walk-through. Project scope included:
Project: Design/Build – B38 Interior Renovations, Navy Fuel Depot, Jacksonville, FL
SCOPE: Design/Build: Remodel of 1200 SF Operations Building. Roof repairs to existing roof. Demolition of existing acoustical ceiling system. Disposal of ceiling fixtures. Demolition of 3 existing bathroom facilities including shower. Install new flooring throughout. Millwork in breakroom. Repair drywall walls and doors. Asbestos Abatement. Plumbing repairs to fractured coupling. Install open-cell insulation in truss area. Re-install all HVAC main ducts and install new flex feeds based on mechanical engineering calculations with new open-cell insulation. New acoustical ceiling with lights installed. All new showers, plumbing fixtures, cabinets, and countertops in bathrooms. New paint on walls and repaired existing doors.
Pictures to follow
Project: Seminole Gate Canopy – NS Mayport, FL
Scope: Design/Build New Guard canopy at south gate of Mayport Naval Station. Scope included specifications, architectural plans, engineering, site modifications, foundations, electrical supply, electrical lighting, grounding systems, canopy structure, structure installation, irrigation modifications, future low-voltage conduit installation, and landscape repairs. KBT self-performed site lay-out, pier forms, canopy erection, irrigation modification, low-voltage conduit, and landscaping. KBT acted a Prime contractor and managed the architect, engineers and surveyor through the design phase, as well as, provided management to other disciplines including concrete placement, electrical, lightning protection, directional boring, and painting.
Project: Maritime Operations Center Renovation, B1878 at NS Mayport, FL
Scope: Renovation of interior office rooms 111B and 112 at building 1878. These rooms are known as the NAVSO Maritime Information Operations Center (MIOC). Project was intended to improve the space functionality and increase capacity in the room. Project included: Framing, Drywall, Acoustical Ceiling grid and tiles, Acoustical wall panels, trims, painting. Project had specific Sound-barrier requirements that had to be met for interior conference room. Project had a crucial, maximum 8-week time frame to minimize the disruption of personnel in the building. KBT successfully completed the project within the allotted 8-week time period.
Photos: The construction area was located in a high-security area, no photos permitted.
Contact Us For Your Next Project!
Take advantage of our use of high-quality subcontractors and cost-effective value engineering. Get in touch with us today to discuss your project and get started with a FREE estimate.
Get in touch with KBT Contracting Corp. for all your full-service residential and commercial construction needs. Contact us today for a FREE estimate!